— Project Summary

Queue ID
Duke-286
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Gilchrist, FL
Region
Southeast
Developer
Masked
IA Status
System Impact Study

BetaActiveSolarDukeLBNL

74.5 MW generation in Gilchrist, FL · In queue since May 2020 · Proposed COD December 2022

74.5 MW

Capacity

1

Components

Solar

5y 10m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 7m

Schedule

39 months past proposed COD

Impact Study25%
Queue EntryMay 29, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

FL

County

Gilchrist

Region

Southeast

Developer

Masked

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Hayfield Substation 230 kV

Data Source

LBNL