BetaActiveSolarDukeLBNL
74.5 MW generation in Gilchrist, FL · In queue since May 2020 · Proposed COD December 2022
74.5 MW
Capacity
1
Components
Solar
5y 10m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 7m
Schedule
39 months past proposed COD
Impact Study25%
Queue EntryMay 29, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
FL
County
Gilchrist
Region
Southeast
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Hayfield Substation 230 kV
Data Source
LBNL