BetaSuspendedSolarDukeLBNL
74.5 MW generation in Alachua, FL · In queue since April 2020 · Proposed COD December 2021
74.5 MW
Capacity
1
Components
Solar
5y 11m
In Queue
Suspended
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 8m
Suspended38%
Queue EntryApr 21, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
FL
County
Alachua
Region
Southeast
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Archer Substation 230 kV
Data Source
LBNL
No news available for this project.