BetaActiveSolarDukeLBNL
74.9 MW generation in Alachua, FL · In queue since March 2020 · Proposed COD July 2025
74.9 MW
Capacity
1
Components
Solar
6 years
In Queue
Construction
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 4m
Schedule
8 months past proposed COD
In Study38%
Queue EntryMar 6, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-31
Project Details
State
FL
County
Alachua
Region
Southeast
Developer
FL Solar 8, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Sunrise Switching Station 69 kV
Data Source
LBNL
No news available for this project.