— Project Summary

Queue ID
Duke-277
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Alachua, FL
Region
Southeast
Developer
FL Solar 8, LLC
IA Status
Construction

BetaActiveSolarDukeLBNL

74.9 MW generation in Alachua, FL · In queue since March 2020 · Proposed COD July 2025

74.9 MW

Capacity

1

Components

Solar

6 years

In Queue

Construction

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5y 4m

Schedule

8 months past proposed COD

In Study38%
Queue EntryMar 6, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-31

Project Details

State

FL

County

Alachua

Region

Southeast

Developer

FL Solar 8, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Sunrise Switching Station 69 kV

Data Source

LBNL

No news available for this project.