— Project Summary

Queue ID
Duke-259
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Highlands, FL
Region
Southeast
Developer
Placid Solar II, LLC
IA Status
Construction

BetaActiveSolarDukeLBNL

74.9 MW generation in Highlands, FL · In queue since May 2019 · Proposed COD October 2022

74.9 MW

Capacity

1

Components

Solar

6y 10m

In Queue

Construction

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 5m

Schedule

42 months past proposed COD

In Study38%
Queue EntryMay 31, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-28

Project Details

State

FL

County

Highlands

Region

Southeast

Developer

Placid Solar II, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Fisheating Creek Substation 230 kV

Data Source

LBNL