74.5 MW generation in Gadsden, FL · In queue since April 2019 · Proposed COD December 2021
74.5 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Suspended
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 8m
Suspended38%
Queue EntryApr 1, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
FL
County
Gadsden
Region
Southeast
Developer
Apalachicola Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Atwater - Liberty 115 kV
Data Source
LBNL