— Project Summary

Queue ID
Duke-24747
Capacity
9.5 MW
Technology
Solar
Status
active
Location
Buncombe, NC
Region
Southeast
Developer
Duke Energy Progress, LLC
IA Status
IA Executed

BetaActiveSolarDukeLBNL

9.5 MW generation in Buncombe, NC · In queue since December 2016 · Proposed COD March 2026

9.5 MW

Capacity

1

Components

Solar

9y 3m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

9y 3m

Construction75%
Queue EntryDec 15, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

NC

County

Buncombe

Region

Southeast

Developer

Duke Energy Progress, LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Asheville Energy Complex

Data Source

LBNL