— Project Summary

Queue ID
Duke-242
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Hernando, FL
Region
Southeast
Developer
Duke Energy Florida, LLC
IA Status
Construction

BetaActiveSolarDukeLBNL

74.9 MW generation in Hernando, FL · In queue since November 2018 · Proposed COD May 2025

74.9 MW

Capacity

1

Components

Solar

7y 4m

In Queue

Construction

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

6y 6m

Schedule

11 months past proposed COD

In Study38%
Queue EntryNov 14, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-10

Project Details

State

FL

County

Hernando

Region

Southeast

Developer

Duke Energy Florida, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Nobleton Substation Or Brooksville - Inverness 69 kV

Data Source

LBNL