BetaActiveOtherDukeLBNL
70 MW generation in Polk, FL · In queue since June 2005 · Proposed COD June 2011
70 MW
Capacity
1
Components
Other
20y 9m
In Queue
IA Executed
IA Status
COD target: 2011
Interconnection Timeline
Total Duration
6 years
Schedule
180 months past proposed COD
Construction75%
Queue EntryJun 7, 2005
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2011-06-01
Project Details
State
FL
County
Polk
Region
Southeast
Developer
NorthernStar
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Vandolah Substation
Data Source
LBNL
No news available for this project.