BetaActiveSolarDukeLBNL
74.5 MW generation in Taylor, FL · In queue since August 2018 · Proposed COD August 2023
74.5 MW
Capacity
1
Components
Solar
7y 7m
In Queue
IA Pending
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5 years
Schedule
31 months past proposed COD
In Study38%
Queue EntryAug 7, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-08-28
Project Details
State
FL
County
Taylor
Region
Southeast
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Perry Substation 69 kV
Data Source
LBNL