— Project Summary

Queue ID
Duke-237
Capacity
74.5 MW
Technology
Solar
Status
suspended
Location
Pasco, FL
Region
Southeast
Developer
Florida Renewable Partners, LLC
IA Status
Suspended

BetaSuspendedSolarDukeLBNL

74.5 MW generation in Pasco, FL · In queue since July 2018 · Proposed COD January 2024

74.5 MW

Capacity

1

Components

Solar

7y 8m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

5y 6m

Suspended38%
Queue EntryJul 17, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-01-19

Project Details

State

FL

County

Pasco

Region

Southeast

Developer

Florida Renewable Partners, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Trilby Substation 69 kV

Data Source

LBNL

No news available for this project.