— Project Summary

Queue ID
Duke-21892
Capacity
2 MW
Technology
Solar
Status
active
Location
Marion, SC
Region
Southeast
Developer
IA Status
Construction

BetaActiveSolarDukeLBNL

2 MW generation in Marion, SC · In queue since July 2018 · Proposed COD March 2024

2 MW

Capacity

1

Components

Solar

7y 8m

In Queue

Construction

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

5y 8m

Schedule

24 months past proposed COD

In Study38%
Queue EntryJul 6, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-03-31

Project Details

State

SC

County

Marion

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Mullins 115kV

Data Source

LBNL

No news available for this project.