BetaActiveSolarDukeLBNL
2 MW generation in Marion, SC · In queue since May 2018 · Proposed COD September 2024
2 MW
Capacity
1
Components
Solar
7y 10m
In Queue
Construction
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
6y 4m
Schedule
19 months past proposed COD
In Study38%
Queue EntryMay 9, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-02
Project Details
State
SC
County
Marion
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Mullins 115kV
Data Source
LBNL
No news available for this project.