BetaActiveBatteryDukeLBNL
50 MW storage in Gaston, NC · In queue since July 2021 · Proposed COD December 2025
50 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 5m
Schedule
4 months past proposed COD
Construction75%
Queue EntryJul 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
NC
County
Gaston
Region
Southeast
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Point of Interconnection
Allen BL 100kV
Data Source
LBNL
No news available for this project.