74.5 MW generation in Levy, FL · In queue since December 2016 · Proposed COD December 2018
74.5 MW
Capacity
1
Components
Solar
9y 3m
In Queue
Construction
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2 years
Schedule
88 months past proposed COD
In Study38%
Queue EntryDec 21, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2018-12-31
Project Details
State
FL
County
Levy
Region
Southeast
Developer
Bronson Solar, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Bronson Substation 230 kV
Data Source
LBNL