— Project Summary

Queue ID
Duke-173
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Levy, FL
Region
Southeast
Developer
Bronson Solar, LLC
IA Status
Construction

BetaActiveSolarDukeLBNL

74.5 MW generation in Levy, FL · In queue since December 2016 · Proposed COD December 2018

74.5 MW

Capacity

1

Components

Solar

9y 3m

In Queue

Construction

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

2 years

Schedule

88 months past proposed COD

In Study38%
Queue EntryDec 21, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2018-12-31

Project Details

State

FL

County

Levy

Region

Southeast

Developer

Bronson Solar, LLC

Utility

Duke Energy Florida

Entity

Duke

Point of Interconnection

Bronson Substation 230 kV

Data Source

LBNL

No news available for this project.