BetaSuspendedSolarDukeLBNL
74.5 MW generation in Hamilton, FL · In queue since December 2016 · Proposed COD May 2023
74.5 MW
Capacity
1
Components
Solar
9y 3m
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 5m
Suspended38%
Queue EntryDec 21, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-26
Project Details
State
FL
County
Hamilton
Region
Southeast
Developer
Florida Renewable Partners, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Suwannee Springs Substation 115 kV
Data Source
LBNL
No news available for this project.