BetaActiveSolarDukeLBNL
74.5 MW generation in Columbia, FL · In queue since July 2016 · Proposed COD May 2023
74.5 MW
Capacity
1
Components
Solar
9y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 10m
Schedule
35 months past proposed COD
Impact Study25%
Queue EntryJul 27, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-19
Project Details
State
FL
County
Columbia
Region
Southeast
Developer
Masked
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Radiant Switching Station 230 kV
Data Source
LBNL