BetaActiveGasDukeLBNL
575 MW generation in Pasco, FL · In queue since November 2015 · Proposed COD November 2025
575 MW
Capacity
1
Components
Gas
10y 4m
In Queue
Construction
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
10 years
Schedule
4 months past proposed COD
In Study38%
Queue EntryNov 10, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-24
Project Details
State
FL
County
Pasco
Region
Southeast
Developer
Shady Hills Energy Center, LLC
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Hudson N Substation Or Brooksville W - Seven Springs 230 kV
Data Source
LBNL
No news available for this project.