BetaActiveSolarDukeLBNL
35 MW generation in Alamance, NC · In queue since March 2020 · Proposed COD June 2025
35 MW
Capacity
1
Components
Solar
6 years
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 3m
Schedule
9 months past proposed COD
Construction75%
Queue EntryMar 9, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-06-26
Project Details
State
NC
County
Alamance
Region
Southeast
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Point of Interconnection
Melville; N/A
Data Source
LBNL
No news available for this project.