BetaActiveOtherDukeLBNL
0.1 MW generation in Marion, FL · In queue since April 2010 · Proposed COD April 2010
0.1 MW
Capacity
1
Components
Other
15y 11m
In Queue
IA Executed
IA Status
COD target: 2010
Interconnection Timeline
Total Duration
<1 month
Schedule
194 months past proposed COD
Construction75%
Queue EntryApr 12, 2010
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2010-04-12
Project Details
State
FL
County
Marion
Region
Southeast
Developer
—
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Maricamp Substation
Data Source
LBNL
No news available for this project.