BetaActiveOtherDukeLBNL
0.8 MW generation in Marion, FL · In queue since April 2009 · Proposed COD July 2009
0.8 MW
Capacity
1
Components
Other
16y 11m
In Queue
IA Executed
IA Status
COD target: 2009
Interconnection Timeline
Total Duration
3 months
Schedule
203 months past proposed COD
Construction75%
Queue EntryApr 15, 2009
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2009-07-31
Project Details
State
FL
County
Marion
Region
Southeast
Developer
—
Utility
Duke Energy Florida
Entity
Duke
Data Source
LBNL
No news available for this project.