BetaActiveSolarDominionLBNL
115 MW generation in Calhoun, SC · Proposed COD June 2029
115 MW
Capacity
1
Components
Solar
—
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
In Study38%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-06-01
Project Details
State
SC
County
Calhoun
Region
Southeast
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Point of Interconnection
Wateree - Orangeburg East 230 kV
Data Source
LBNL
No news available for this project.