BetaActiveGasDominionLBNL
337.5 MW generation in Colleton, SC · Proposed COD December 2029
337.5 MW
Capacity
1
Components
Gas
—
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
In Study38%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
SC
County
Colleton
Region
Southeast
Developer
DESC - Generation
Utility
Dominion Energy South Carolina
Entity
Dominion
Point of Interconnection
Canadys 230kV Substation
Data Source
LBNL
No news available for this project.