199 MW storage in Berkeley, SC · Proposed COD December 2028
199 MW
Capacity
1
Components
Battery
—
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Pre-Study0%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
SC
County
Berkeley
Region
Southeast
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Point of Interconnection
Williams - Goose Creek 115 kV
Data Source
LBNL
No news available for this project.