47.7 MW generation in Lexington, SC · Proposed COD September 2023
47.7 MW
Capacity
1
Components
Hydro
—
In Queue
—
IA Status
COD target: 2023
Interconnection Timeline
Schedule
31 months past proposed COD
Pre-Study0%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-09-01
Project Details
State
SC
County
Lexington
Region
Southeast
Developer
DESC - Generation
Utility
Dominion Energy South Carolina
Entity
Dominion
Point of Interconnection
Saluda Hydro 115 kV Substation
Data Source
LBNL