BetaActiveSolarDominionLBNL
60 MW generation in Aiken, SC · Proposed COD March 2028
60 MW
Capacity
1
Components
Solar
—
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Pre-Study0%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
SC
County
Aiken
Region
Southeast
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Point of Interconnection
Urquhart - SRS 51 115kV
Data Source
LBNL
No news available for this project.