— Project Summary

Queue ID
Dominion-20230828002
Capacity
54 MW
Technology
Solar+Battery
Status
active
Location
Orangeburg, SC
Region
Southeast
Developer
IA Status

BetaActiveSolarBatteryDominionLBNL

54 MW hybrid in Orangeburg, SC · Proposed COD August 2026

54 MW

Capacity

1

Components

Solar

In Queue

IA Status

COD target: 2026

Interconnection Timeline
Pre-Study0%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-01

Project Details

State

SC

County

Orangeburg

Region

Southeast

Developer

Utility

Dominion Energy South Carolina

Entity

Dominion

Point of Interconnection

Orangeburg East - St. George 115 kV #1

Data Source

LBNL