BetaActiveSolarDominionLBNL
2.5 MW generation in Aiken, SC · Proposed COD July 2024
2.5 MW
Capacity
1
Components
Solar
—
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Schedule
20 months past proposed COD
Pre-Study0%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-07-31
Project Details
State
SC
County
Aiken
Region
Southeast
Developer
—
Utility
Dominion Energy South Carolina
Entity
Dominion
Point of Interconnection
Aiken - Southeastern Clay 46 kV
Data Source
LBNL
No news available for this project.