— Project Summary

Queue ID
Dominion-20230825002
Capacity
2.5 MW
Technology
Solar
Status
active
Location
Aiken, SC
Region
Southeast
Developer
IA Status

BetaActiveSolarDominionLBNL

2.5 MW generation in Aiken, SC · Proposed COD July 2024

2.5 MW

Capacity

1

Components

Solar

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Schedule

20 months past proposed COD

Pre-Study0%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-31

Project Details

State

SC

County

Aiken

Region

Southeast

Developer

Utility

Dominion Energy South Carolina

Entity

Dominion

Point of Interconnection

Aiken - Southeastern Clay 46 kV

Data Source

LBNL

No news available for this project.