— Project Summary

Queue ID
Dominion-20230609002
Capacity
100 MW
Technology
Battery
Status
active
Location
Orangeburg, SC
Region
Southeast
Developer
IA Status

BetaActiveBatteryDominionLBNL

100 MW storage in Orangeburg, SC · Proposed COD June 2026

100 MW

Capacity

1

Components

Battery

In Queue

IA Status

COD target: 2026

Interconnection Timeline
Pre-Study0%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

SC

County

Orangeburg

Region

Southeast

Developer

Utility

Dominion Energy South Carolina

Entity

Dominion

Point of Interconnection

Saluda River - St. George 230 kV

Data Source

LBNL