— Project Summary

Queue ID
CSU-CSU-2023-3
Capacity
300 MW
Technology
Solar
Status
active
Location
El Paso, CO
Region
West
Developer
IA Status
Feasibility Study

BetaActiveSolarCSULBNL

300 MW generation in El Paso, CO · In queue since May 2023 · Proposed COD January 2026

300 MW

Capacity

1

Components

Solar

2y 10m

In Queue

Feasibility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 8m

Schedule

2 months past proposed COD

Feasibility Study13%
Queue EntryMay 8, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-11

Project Details

State

CO

County

El Paso

Region

West

Developer

Utility

Colorado Springs Utilities

Entity

CSU

Point of Interconnection

Williams Creek Substation

Data Source

LBNL

No news available for this project.