BetaActiveSolarCSULBNL
300 MW generation in El Paso, CO · In queue since May 2023 · Proposed COD January 2026
300 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Feasibility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 8m
Schedule
2 months past proposed COD
Feasibility Study13%
Queue EntryMay 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-11
Project Details
State
CO
County
El Paso
Region
West
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Point of Interconnection
Williams Creek Substation
Data Source
LBNL
No news available for this project.