— Project Summary

Queue ID
CSU-CSU-2023-1
Capacity
105 MW
Technology
Battery
Status
active
Location
El Paso, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveBatteryCSULBNL

105 MW storage in El Paso, CO · In queue since April 2023 · Proposed COD July 2025

105 MW

Capacity

1

Components

Battery

2y 11m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 3m

Schedule

9 months past proposed COD

Impact Study25%
Queue EntryApr 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-01

Project Details

State

CO

County

El Paso

Region

West

Developer

Utility

Colorado Springs Utilities

Entity

CSU

Point of Interconnection

Horizon Substation

Data Source

LBNL

No news available for this project.