BetaActiveBatteryCSULBNL
105 MW storage in El Paso, CO · In queue since April 2023 · Proposed COD July 2025
105 MW
Capacity
1
Components
Battery
2y 11m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 3m
Schedule
9 months past proposed COD
Impact Study25%
Queue EntryApr 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-01
Project Details
State
CO
County
El Paso
Region
West
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Point of Interconnection
Horizon Substation
Data Source
LBNL
No news available for this project.