— Project Summary

Queue ID
CSU-CSU-2022-3
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
El Paso, CO
Region
West
Developer
IA Status
Feasibility Study

BetaActiveSolarBatteryCSULBNL

200 MW hybrid in El Paso, CO · In queue since February 2023 · Proposed COD August 2026

200 MW

Capacity

1

Components

Solar

3y 1m

In Queue

Feasibility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Feasibility Study13%
Queue EntryFeb 2, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-01

Project Details

State

CO

County

El Paso

Region

West

Developer

Utility

Colorado Springs Utilities

Entity

CSU

Point of Interconnection

Williams Creek- Horizon Line

Data Source

LBNL

No news available for this project.