BetaActiveSolarCSULBNL
100 MW generation in El Paso, CO · In queue since September 2022 · Proposed COD January 2025
100 MW
Capacity
1
Components
Solar
3y 6m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 4m
Schedule
15 months past proposed COD
Impact Study25%
Queue EntrySep 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Project Details
State
CO
County
El Paso
Region
West
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Point of Interconnection
Nixon Substation
Data Source
LBNL
No news available for this project.