— Project Summary

Queue ID
CSU-CSU-2022-2
Capacity
100 MW
Technology
Solar
Status
active
Location
El Paso, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarCSULBNL

100 MW generation in El Paso, CO · In queue since September 2022 · Proposed COD January 2025

100 MW

Capacity

1

Components

Solar

3y 6m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 4m

Schedule

15 months past proposed COD

Impact Study25%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-01

Project Details

State

CO

County

El Paso

Region

West

Developer

Utility

Colorado Springs Utilities

Entity

CSU

Point of Interconnection

Nixon Substation

Data Source

LBNL

No news available for this project.