BetaActiveWindCSULBNL
500 MW generation in Lincoln, CO · In queue since July 2021 · Proposed COD December 2025
500 MW
Capacity
1
Components
Wind
4y 8m
In Queue
System Impact Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 5m
Schedule
3 months past proposed COD
Impact Study25%
Queue EntryJul 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
CO
County
Lincoln
Region
West
Developer
—
Utility
Colorado Springs Utilities
Entity
CSU
Point of Interconnection
Williams Creek
Data Source
LBNL
No news available for this project.