— Project Summary

Queue ID
CSU-CSU-2021-2
Capacity
500 MW
Technology
Wind
Status
active
Location
Lincoln, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveWindCSULBNL

500 MW generation in Lincoln, CO · In queue since July 2021 · Proposed COD December 2025

500 MW

Capacity

1

Components

Wind

4y 8m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 5m

Schedule

3 months past proposed COD

Impact Study25%
Queue EntryJul 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

CO

County

Lincoln

Region

West

Developer

Utility

Colorado Springs Utilities

Entity

CSU

Point of Interconnection

Williams Creek

Data Source

LBNL