BetaActiveGasCLPTLBNL
130 MW generation in Laramie, WY · In queue since May 2024 · Proposed COD January 2029
130 MW
Capacity
1
Components
Gas
1y 10m
In Queue
Cluster Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 8m
Impact Study25%
Queue EntryMay 30, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-01
Project Details
State
WY
County
Laramie
Region
West
Developer
Cheyenne Light, Fuel & Power
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Point of Interconnection
Cheyenne Prairie Substation
Data Source
LBNL
No news available for this project.