115 MW generation in Laramie, WY · In queue since May 2024 · Proposed COD January 2029
115 MW
Capacity
1
Components
Gas
1y 10m
In Queue
Cluster Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 8m
Impact Study25%
Queue EntryMay 30, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-01
Project Details
State
WY
County
Laramie
Region
West
Developer
Black Hills Electric Generation
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Point of Interconnection
Cheyenne Prairie Substation
Data Source
LBNL