— Project Summary

Queue ID
CLPT-CLPT G29
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Laramie, WY
Region
West
Developer
IA Status
Cluster Study

BetaActiveSolarWindBatteryCLPTLBNL

150 MW hybrid in Laramie, WY · In queue since May 2024 · Proposed COD December 2027

150 MW

Capacity

1

Components

Solar

1y 10m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 7m

Impact Study25%
Queue EntryMay 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

WY

County

Laramie

Region

West

Developer

Utility

Black Hills Cheyenne Light Fuel and Power Transmission

Entity

CLPT

Point of Interconnection

Wallick 115 kV Substation

Data Source

LBNL

No news available for this project.