— Project Summary

Queue ID
CLPT-CLPT G23
Capacity
150 MW
Technology
Wind
Status
active
Location
Laramie, WY
Region
West
Developer
IA Status
Facility Study

BetaActiveWindCLPTLBNL

150 MW generation in Laramie, WY · In queue since February 2023 · Proposed COD December 2026

150 MW

Capacity

1

Components

Wind

3y 1m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 10m

Facilities Study50%
Queue EntryFeb 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

WY

County

Laramie

Region

West

Developer

Utility

Black Hills Cheyenne Light Fuel and Power Transmission

Entity

CLPT

Point of Interconnection

Bison 115 kV Substation

Data Source

LBNL

No news available for this project.