BetaActiveGasCLPTLBNL
125 MW generation in Laramie, WY · In queue since November 2022 · Proposed COD June 2024
125 MW
Capacity
1
Components
Gas
3y 4m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 7m
Schedule
22 months past proposed COD
Facilities Study50%
Queue EntryNov 23, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
WY
County
Laramie
Region
West
Developer
Black Hills Electric Generation
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Point of Interconnection
Cheyenne Prairie Substation
Data Source
LBNL
No news available for this project.