— Project Summary

Queue ID
CLPT-CLPT G17
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Laramie, WY
Region
West
Developer
NextEra Energy Resources Interconnection Holdings, LL
IA Status
IA Executed

BetaActiveSolarWindBatteryCLPTLBNL

300 MW hybrid in Laramie, WY · In queue since April 2022 · Proposed COD December 2025

300 MW

Capacity

1

Components

Solar

3y 11m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 8m

Schedule

3 months past proposed COD

Construction75%
Queue EntryApr 1, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

WY

County

Laramie

Region

West

Developer

NextEra Energy Resources Interconnection Holdings, LL

Utility

Black Hills Cheyenne Light Fuel and Power Transmission

Entity

CLPT

Point of Interconnection

East Business Park 115kV Substation

Data Source

LBNL

No news available for this project.