300 MW hybrid in Laramie, WY · In queue since April 2022 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
3y 11m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
3y 8m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-31
State
WY
County
Laramie
Region
West
Developer
NextEra Energy Resources Interconnection Holdings, LL
Utility
Black Hills Cheyenne Light Fuel and Power Transmission
Entity
CLPT
Point of Interconnection
East Business Park 115kV Substation
Data Source
LBNL