SUNSHINE VALLEY SOLAR 1 — Project Summary

Queue ID
CAISO-993
Capacity
90 MW
Technology
Solar+Battery
Status
active
Location
Nye, NV
Region
CAISO
Developer
IA Status
IA Executed

SUNSHINE VALLEY SOLAR 1

BetaActiveSolarBatteryCAISOLBNL + Live

90 MW hybrid in Nye, NV · In queue since April 2013 · Proposed COD December 2026

90 MW

Capacity

2

Components

Solar + Battery

12y 11m

In Queue

IA Executed

IA Status

Signed Aug 2017

Interconnection Timeline

Queue → IA

4y 4m

IA → COD

9y 4m

Total Duration

4y 4m

Construction75%
Queue EntryApr 30, 2013

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementAug 7, 2017

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-31

Technology
Solar50 MW · 56%
Battery40 MW · 44%
Project Details

State

NV

County

Nye

Region

CAISO

Developer

Utility

VEA

Entity

CAISO

Point of Interconnection

Valley Substation 138 kV

Data Source

LBNL + Live

No news available for this project.