SUNSHINE VALLEY SOLAR 1
BetaActiveSolarBatteryCAISOLBNL + Live
90 MW hybrid in Nye, NV · In queue since April 2013 · Proposed COD December 2026
90 MW
Capacity
2
Components
Solar + Battery
12y 11m
In Queue
IA Executed
IA Status
Signed Aug 2017
Interconnection Timeline
Queue → IA
4y 4m
IA → COD
9y 4m
Total Duration
4y 4m
Construction75%
Queue EntryApr 30, 2013
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementAug 7, 2017
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-12-31
Technology
Solar50 MW · 56%
Battery40 MW · 44%
Project Details
State
NV
County
Nye
Region
CAISO
Developer
—
Utility
VEA
Entity
CAISO
Point of Interconnection
Valley Substation 138 kV
Data Source
LBNL + Live