BOTTLE ROCK POWER
BetaActiveGeothermalBatteryCAISOLBNL + Live
56.882 MW hybrid in Lake, CA · In queue since September 2005 · Proposed COD November 2027
56.882 MW
Capacity
2
Components
Geothermal + Battery
20y 6m
In Queue
IA Executed
IA Status
Signed Nov 2006
Interconnection Timeline
Queue → IA
1y 2m
IA → COD
21 years
Total Duration
1y 2m
Construction75%
Queue EntrySep 13, 2005
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementNov 16, 2006
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-11-30
Technology
Geothermal9.435 MW · 17%
Battery47.447 MW · 83%
Project Details
State
CA
County
Lake
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Geysers #17-Fulton 230 kV Line
Data Source
LBNL + Live
No news available for this project.