WRIGHT SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
280 MW hybrid in Merced, CA · In queue since March 2011 · Proposed COD October 2026
280 MW
Capacity
2
Components
Solar + Battery
15 years
In Queue
IA Executed
IA Status
Signed Mar 2014
Interconnection Timeline
Queue → IA
3 years
IA → COD
12y 7m
Total Duration
3 years
Construction75%
Queue EntryMar 31, 2011
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMar 21, 2014
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-10-21
Technology
Solar200 MW · 71%
Battery80 MW · 29%
Project Details
State
CA
County
Merced
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Los Banos-Panoche #1 230kV Line
Data Source
LBNL + Live