REDWOOD SOLAR FARM
BetaActiveSolarCAISOLBNL + Live
90 MW generation in Kern, CA · In queue since March 2011 · Proposed COD July 2024
90 MW
Capacity
1
Components
Solar
15 years
In Queue
IA Executed
IA Status
Signed Aug 2013
Interconnection Timeline
Queue → IA
2y 5m
IA → COD
10y 11m
Total Duration
2y 5m
Schedule
21 months past proposed COD
Construction75%
Queue EntryMar 31, 2011
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementAug 23, 2013
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-07-01
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Lamont 115 KV
Data Source
LBNL + Live
No news available for this project.