REDWOOD SOLAR FARM — Project Summary

Queue ID
CAISO-744
Capacity
90 MW
Technology
Solar
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

REDWOOD SOLAR FARM

BetaActiveSolarCAISOLBNL + Live

90 MW generation in Kern, CA · In queue since March 2011 · Proposed COD July 2024

90 MW

Capacity

1

Components

Solar

15 years

In Queue

IA Executed

IA Status

Signed Aug 2013

Interconnection Timeline

Queue → IA

2y 5m

IA → COD

10y 11m

Total Duration

2y 5m

Schedule

21 months past proposed COD

Construction75%
Queue EntryMar 31, 2011

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementAug 23, 2013

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2024-07-01

Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Lamont 115 KV

Data Source

LBNL + Live