LASSEN LODGE HYDROELECTRIC
BetaActiveHydroCAISOLBNL + Live
4.5 MW generation in Tehama, CA · In queue since March 2011 · Proposed COD October 2027
4.5 MW
Capacity
1
Components
Hydro
15 years
In Queue
IA Executed
IA Status
Signed May 2013
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
14y 5m
Total Duration
2y 2m
Construction75%
Queue EntryMar 31, 2011
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMay 21, 2013
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2027-10-15
Project Details
State
CA
County
Tehama
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Vota-South 60 kV
Data Source
LBNL + Live
No news available for this project.