LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECT
BetaActivePumped StorageCAISOLBNL + Live
500 MW storage in Riverside, CA · In queue since June 2005 · Proposed COD December 2028
500 MW
Capacity
1
Components
Pumped Storage
20y 9m
In Queue
IA Executed
IA Status
Signed Aug 2012
Interconnection Timeline
Queue → IA
7y 2m
IA → COD
16y 4m
Total Duration
7y 2m
Construction75%
Queue EntryJun 21, 2005
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementAug 11, 2012
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Proposed Lee Lake Substation 500 kV
Data Source
LBNL + Live
No news available for this project.