LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECT — Project Summary

Queue ID
CAISO-72
Capacity
500 MW
Technology
Battery
Status
active
Location
Riverside, CA
Region
CAISO
Developer
IA Status
IA Executed

LAKE ELSINORE ADVANCED PUMPED STORAGE PROJECT

BetaActivePumped StorageCAISOLBNL + Live

500 MW storage in Riverside, CA · In queue since June 2005 · Proposed COD December 2028

500 MW

Capacity

1

Components

Pumped Storage

20y 9m

In Queue

IA Executed

IA Status

Signed Aug 2012

Interconnection Timeline

Queue → IA

7y 2m

IA → COD

16y 4m

Total Duration

7y 2m

Construction75%
Queue EntryJun 21, 2005

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementAug 11, 2012

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

CA

County

Riverside

Region

CAISO

Developer

Utility

SDGE

Entity

CAISO

Point of Interconnection

Proposed Lee Lake Substation 500 kV

Data Source

LBNL + Live

No news available for this project.