EXCELSIOR SOLAR (FKA: BURFORD FIVE POINTS)
BetaActiveSolarBatteryCAISOLBNL + Live
120 MW hybrid in Fresno, CA · In queue since March 2011 · Proposed COD December 2024
120 MW
Capacity
2
Components
Solar + Battery
15 years
In Queue
IA Executed
IA Status
Signed Mar 2014
Interconnection Timeline
Queue → IA
3 years
IA → COD
10y 9m
Total Duration
3 years
Schedule
15 months past proposed COD
Construction75%
Queue EntryMar 31, 2011
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMar 12, 2014
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-12-20
Technology
Solar60 MW · 50%
Battery60 MW · 50%
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Panoche-Schindler #1 and #2 115 kV Line
Data Source
LBNL + Live