KETTLEMAN SOLAR PROJECT (FKA KETTLEMAN SOLAR FARM) — Project Summary

Queue ID
CAISO-625
Capacity
40 MW
Technology
Solar+Battery
Status
active
Location
Kings, CA
Region
CAISO
Developer
IA Status
IA Executed

KETTLEMAN SOLAR PROJECT (FKA KETTLEMAN SOLAR FARM)

BetaActiveSolarBatteryCAISOLBNL + Live

40 MW hybrid in Kings, CA · In queue since May 2010 · Proposed COD April 2025

40 MW

Capacity

2

Components

Solar + Battery

15y 10m

In Queue

IA Executed

IA Status

Signed Oct 2012

Interconnection Timeline

Queue → IA

2y 5m

IA → COD

12y 6m

Total Duration

2y 5m

Schedule

12 months past proposed COD

Construction75%
Queue EntryMay 14, 2010

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementOct 17, 2012

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-04-01

Technology
Solar20 MW · 50%
Battery20 MW · 50%
Project Details

State

CA

County

Kings

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Henrietta-Tulare Lake 70 kV

Data Source

LBNL + Live

No news available for this project.