Soledad Solar
562.502 MW hybrid in Kern, CA · In queue since April 2023 · Proposed COD June 2028
562.502 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
WINDHUB 230 kV
Data Source
LBNL
Residents question battery-storage safety in Canyon Country
About 50 people gathered Thursday at the Canyon Country Community Center, as city officials sought to address recent questions they've...
Tony Maldonado | The Ticking Time Bomb
I am urgently requesting an immediate investigation into the lithium battery storage facility approved and constructed at 18358 Soledad Canyon Road in Santa...
Last updated 2026-03-26