Pinecone
BetaActiveBatteryCAISOLBNL
514.599 MW storage in Yuma, AZ · In queue since April 2023 · Proposed COD April 2028
514.599 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Not Started
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntryApr 17, 2023
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-14
Project Details
State
AZ
County
Yuma
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Hassayampa-Hoodoo Wash
Data Source
LBNL
No news available for this project.