Nyquist Storage — Project Summary

Queue ID
CAISO-55042
Capacity
199.68 MW
Technology
Battery
Status
active
Location
Riverside, CA
Region
CAISO
Developer
IA Status
Not Started

Nyquist Storage

BetaActiveBatteryCAISOLBNL

199.68 MW storage in Riverside, CA · In queue since April 2023 · Proposed COD March 2031

199.68 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Not Started

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

7y 11m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-03-01

Project Details

State

CA

County

Riverside

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

COLORADO RIVER 230 kV

Data Source

LBNL

No news available for this project.